The Canavaccio plant generates a growing share of the energy it uses. This is not a finished project but an open building site, and this page says where it stands, using meter readings.
Where we are today
650 kWp of solar capacity on the plant, built in four stages:
| Plant | Capacity | Status |
|---|---|---|
| Canopy | 30 kW | running, outside the monitoring system |
| Revamping of the first plant | 120 kW | completed in May 2025 |
| First extension | 100 kW | running since September 2025 |
| New plant | 400 kW | installed, waiting for grid connection |
Over the last twelve months the plants already running produced 290,124 kWh, measured at the inverter meters. That is 1,319 kWh for every kWp installed, in line with the yield expected in the Marche region.
Once the 400 kW are connected, expected output rises to around 820,000 kWh a year. That figure is a projection, not a measurement: the 290,124 kWh are the certain number.

What our monitoring system reports over the 362 days shown: 169,782 kg of CO₂ not emitted.
What it adds up to over a year
A sunny day says little: what counts is twelve months, nights and winter included. From September 2025 to August 2026, the last full year with the whole system metered:
| 83.7% | of the solar energy generated is used on site, rather than sold back to the grid |
| 19.5% | of the plant's demand is covered by the sun |
| ~60% | of the electricity we use is low carbon |
The figures behind them: 290,642 kWh generated, 1,006,279 kWh drawn from the grid, 47,457 kWh fed back, for a total consumption of 1,249,464 kWh. The first two come from meters; the third is an estimate, because it depends on how much fossil generation the Italian grid carries (49% on average over those twelve months).
This is where the work in progress shows. With the 400 kW connected, the share of demand covered by the sun goes from 19.5% to around 50%: that is the step we are taking, and the reason this page exists.
How we keep track
Energy at the plant is monitored continuously: what the plants generate, what the shop floor uses, what goes into the grid and what comes out of it. The figures come from inverters and meters, not from estimates.

A day in September 2026: in blue the energy drawn from the grid, in orange the solar generation, in purple what goes back to the grid when generation exceeds consumption.
Monitoring is the basis of the Energy Management System certified to UNI EN ISO 50001: the statement is here.
What is still missing
- Final grid connection of the 400 kW, for which we are waiting on authorisation.
- Connecting the canopy to the monitoring system: today it generates, but we cannot read it.
The rest of our work on consumption and waste (lighting, motor inverters, waste separation) is on the Sustainability page.